The TMS Go-Live Checklist: From Data Conversion to First Settlement Run

A TMS go-live is not one day. It is a sequence of conversions, tests, and sign-offs that ends when the first settlements pay correctly and the first month closes clean. Use these phased checklists to keep the cutover controlled.

Data conversionRates & FSCEDI & ELDCutover weekend

Go-live is a process, not a date

Every carrier remembers its TMS go-live. For some, it was a smooth Monday: dispatch logged in, loads moved, invoices went out on Tuesday, and drivers were paid correctly on Friday. For others, it was weeks of re-rated loads, missing accessorials, rejected EDI invoices, and drivers calling about short settlements.

The difference is rarely the software. It is preparation. Since 2008, Strong Tower Consulting has supported carrier installations, conversions, upgrades, and on-site go-live weeks, and the pattern holds: the go-lives that go well are the ones where data was cleaned early, rates were tested against real loads, trading partners were certified ahead of time, people were trained on their own work, and the cutover was rehearsed.

This checklist is organized by phase. Adapt it to your system and your operation, but do not skip a phase. Each one protects the next.

Phase 0: Governance and go/no-go criteria

Before anyone converts a record, agree on how the project will be run and how you will decide you are ready.

ItemOwnerDone when
Executive sponsor namedOwner / presidentOne person can make final calls on scope, date, and spend
Project manager namedSponsorOwns the plan, the issues log, and the weekly status
Department leads namedSponsorDispatch, billing, settlements, safety, accounting, and IT each have a decision-maker
Go-live date selectedSponsor and PMAvoids month-end, peak season, holidays, and settlement day
Go/no-go criteria writtenPM and leadsSpecific tests that must pass, signed off in advance
Rollback plan writtenPM and ITClear point of no return and how to revert before it

Write the go/no-go criteria early, while nobody is under deadline pressure. Typical criteria: rating tests pass on an agreed sample of loads, a test settlement matches the old system, every EDI trading partner is certified or has a manual fallback, opening balances reconcile, and every user has completed role training.

Phase 1: Master data conversion

Bad data in the old system becomes bad data in the new one, only faster. Clean before you convert.

Data setChecklist
Customers and bill-to accountsMerge duplicates; confirm bill-to vs. shipper vs. consignee relationships; credit limits and terms; invoice delivery method and required paperwork
LocationsStandardize addresses; confirm geocodes or mileage points; hours, appointment rules, and special instructions
DriversPay profiles, home terminal, hire dates, license and medical card dates, deduction and escrow setups
Owner-operators and carriersLease or carrier agreements, pay terms, insurance, authority, remit-to and 1099 details
EquipmentTractors, trailers, and containers with unit numbers, ownership, and maintenance status
VendorsFuel, repair, lumpers, and other payees mapped to accounting
Users and securityRoles and permissions by job, not by person; nobody gets admin by default

Run at least two test loads of the converted data before the final conversion. After each, have the people who use the data check it. A billing clerk will spot a wrong bill-to in seconds that an analyst might miss for weeks.

Phase 2: Rates, tariffs, and fuel surcharge tables

Rating is where go-lives quietly lose money. A missing accessorial or a wrong FSC table does not crash anything. It just under-bills, load after load, until someone notices.

  • Inventory every rate source: customer contracts, tariffs, spot quotes, lane rates, minimums, and mileage bases.
  • Retire dead rates before conversion instead of moving them across.
  • Build fuel surcharge tables per customer agreement: index source, update day, peg price, increment, and calculation method.
  • Set up accessorials: detention, layover, stop-offs, tarping, lumper reimbursement, TONU, driver assist, and hazmat, with the rules for when each applies.
  • Pick a test sample of real recent loads that covers every major customer, lane type, and accessorial.
  • Rate the sample in both systems and reconcile every difference to a cause before sign-off.
  • Confirm mileage settings such as routing type and version match what customers were billed under.

Phase 3: EDI trading partners

Your largest shippers likely tender and pay through EDI. A broken 204 or 210 at go-live can mean lost tenders or rejected invoices, so treat each trading partner as its own mini-project.

TransactionWhat to test
204 Load TenderTenders create orders correctly with stops, references, and appointment times
990 ResponseAccept and decline responses reach the partner within their acceptance window
214 StatusPickup, delivery, and in-transit statuses fire with the codes the partner expects
210 InvoiceInvoice totals, accessorial codes, and references match the partner's requirements
997 AcknowledgmentFunctional acknowledgments are sent and received; rejects are monitored
  • List every partner, transaction set, and connection method.
  • Confirm identifiers, qualifiers, and any connection changes with each partner well before go-live.
  • Schedule partner testing early. Many shippers need lead time to test and certify.
  • Plan the switch so tenders in flight are not lost or duplicated at cutover.
  • Agree on a manual fallback, such as email tenders or portal invoicing, for any partner not certified in time.

Phase 4: ELD, telematics, and other interfaces

  • ELD and telematics: unit and driver IDs mapped correctly; positions, HOS data, and messages flowing; load assignments reaching the cab if your workflow uses them.
  • Mileage and routing: the same settings used for rating, pay, and fuel tax reporting.
  • Fuel cards: transaction imports mapped to drivers and units; advances and fuel purchases flowing to settlements and fuel tax records.
  • Document imaging: scans attach to the right orders; PODs available to billing; historical images still reachable.
  • Customer tracking or portals: statuses and documents visible to customers as before.

Test each interface with live-like data, then test the whole chain: tender in, dispatch, ELD status, delivery, POD, invoice, settlement.

Phase 5: Accounting and settlements

The first settlement run is the moment drivers judge the new system. Get it right.

ItemChecklist
Chart of accounts mappingRevenue, accessorial, fuel surcharge, pay, and deduction codes post to the right GL accounts
Opening AROpen invoices converted; aging totals match the old system to the penny
Opening AP and payablesOpen vendor and carrier payables converted and reconciled
Driver balancesEscrow balances, advance balances, loan and recurring deduction balances converted and confirmed
Pay rulesMileage, percentage, hourly, stop pay, and detention pay tested on real trips
Test settlementRun a settlement period in both systems and compare driver by driver
Statements and chequesInvoices, settlement statements, and cheque layouts printed and approved

Have payroll staff and, if possible, a couple of trusted drivers or owner-operators review test settlement statements. If a driver cannot read the statement, you will hear about it on Friday.

Phase 6: Training

  • Train by role: customer service, dispatch, billing, settlements, safety, maintenance, and management.
  • Use your own customers, lanes, and loads in the training environment, not generic demo data.
  • Train close to go-live so skills are fresh, with a refresher the week before.
  • Name and train super-users in each department who will be the first line of help.
  • Provide short written job aids for the top tasks in each role.
  • Confirm every user can log in with the right permissions before cutover weekend.

Phase 7: Cutover weekend

Write the cutover as an hour-by-hour runbook with owners, and rehearse it at least once.

WhenTask
Before freezeFull backup of the old system; confirm it restores
FreezeStop new entry in the old system; capture final open orders, loads in transit, and balances
ConversionRun final data conversion; load open orders and in-transit loads
ReconciliationCompare counts and totals: customers, open orders, AR aging, AP, driver balances
InterfacesSwitch EDI, ELD, fuel card, and imaging connections; send test transactions
Smoke testDepartment leads enter, dispatch, and bill test loads end to end
Go/no-goSponsor reviews criteria and makes the call
Old systemSet to read-only for lookups and history

Staffing go-live week

Go-live week is not the time to run lean. Freight does not slow down because you changed systems, and every new screen takes a little longer the first few times. Plan the people before you plan the parties.

RoleGo-live week responsibility
Floor supportExperienced implementers sitting with dispatch, billing, and payroll, answering questions at the desk
Super-usersFirst line of help in each department; log issues they cannot solve
Issues coordinatorOwns the issues log; assigns, tracks, and closes every item
Vendor supportNamed contacts on call, with an agreed escalation path for system defects
Interface watcherMonitors EDI, ELD, fuel card, and imaging queues throughout the day
SponsorAvailable daily to make scope and priority calls quickly

Consider lightening the load where you can: avoid onboarding new customers, launching new lanes, or starting other projects the same week. Tell your key customers and drivers that you are changing systems, who to call with questions, and what, if anything, will look different on their invoices or settlement statements.

Day 1, week 1, and month 1

Day 1

  • Support staff on the floor at start of shift, in every department.
  • Morning stand-up and end-of-day review of every issue.
  • Watch EDI queues for rejected tenders and missing 214s.
  • Confirm ELD positions and statuses are updating.

Week 1

  • Review the first invoices before they go out; check rates, FSC, and accessorials.
  • Confirm first 210s are accepted by trading partners.
  • Triage the issues log daily: fix, train, or defer with an owner.
  • Run the first settlement with extra review time and compare a sample to expected pay.

Month 1

  • Close the first month and reconcile the TMS to the general ledger.
  • Check AR aging against expectations; look for invoices stuck on billing holds.
  • Run fuel tax and mileage reports and confirm the data looks right.
  • Hold a lessons-learned session and schedule refresher training where needed.
  • Close or schedule every remaining punch-list item.

Common go-live mistakes

  • Converting dirty data and planning to clean it "after go-live."
  • Testing rates on a handful of easy loads instead of a representative sample.
  • Starting EDI partner testing too late.
  • Training too early, or training on generic data.
  • Going live on month-end or right before settlement day.
  • No written rollback plan or go/no-go criteria.
  • Sending vendor support home on Tuesday.

How Strong Tower Consulting helps

Strong Tower Consulting has planned and supported carrier go-lives since 2008, including on-site go-live weeks, data conversions, and staff training. Our TMS Implementation & Go-Live practice covers data conversion, testing, cutover planning, and floor support. Project & Program Management keeps vendors and internal teams on plan, Training & Enablement builds role-based training on your own freight, and ELD, EDI & Back-Office Integration handles trading partner and interface testing.

Independent by design

Strong Tower Consulting never requires you to buy our software. We support go-lives on the system you chose, and our only goal is a clean cutover and a first settlement run your drivers trust.

Frequently asked questions

What is the best day to go live on a new TMS?

Most carriers cut over over a weekend so the office can go live on a lighter day with full staff and vendor support present. Avoid month-end, quarter-end, peak season, and the days right before a settlement run or a major holiday.

Should we run the old and new TMS in parallel?

A full parallel run doubles the workload, so most carriers parallel only the high-risk outputs: rating a sample of loads in both systems, running a settlement in both and comparing, and reconciling invoices. Keep the old system available read-only for history and lookups.

How much history should we convert into the new TMS?

Convert all active master data, open orders, and open AR and AP balances. For history, decide based on reporting, audit, and claims needs. Many carriers convert a limited window and keep older history accessible in the old system or a reporting database.

When is a TMS implementation really finished?

Not at go-live. Plan on the first month as stabilization. The implementation is finished when billing, settlements, EDI, and the first month-end close all run cleanly, and the punch list is closed or scheduled.

Do we have to buy software from you to get go-live help?

No. Strong Tower Consulting is independent and supports go-lives on the TMS you selected. Consulting never requires buying our sister company's software.

Start Here

Go live without the cleanup weeks.

Strong Tower Consulting plans the conversion, tests the rates and EDI, trains your people, and stands on the floor with you through cutover.